Roy Thomas Powell
Page 1 June 8th, 2015 Roy Thomas Powell 87 Leavitt Street Mexico, Maine 04257 207-577-6085 masterguide@earthlink.net Project Controls Manager/Program Management Lead Summary A Lead
Project Scheduler and Project Controls Manager with over twenty five years of
Primavera project scheduling, project controls management, and construction
management experience involving power generation and T&D. Has built and
maintained complex Primavera project schedules for major T&D and power
generation projects. Scheduling expertise includes developing schedule
baselines and manloading, creating work breakdown structures, performing
critical path analyses, cost and resource loading, project controls
forecasting, earned value analyses, and custom layouts and reports. T&D scheduling
experience includes developing 31 project schedules in interactive PERT
format for bid proposals and planned construction as well as developing,
rebuilding, and maintaining Primavera project schedules for extensive
overland and underground transmission construction. Power generation
scheduling experiences includes developing CPM project schedules in Primavera
for nuclear, wind, and hydro power plant construction and upgrades. Proven
ability to effectively control project risk and accurately forecast / track
costs. Is a Primavera expert with experience training project staff in
CPM planning / scheduling and project controls methodology. In a recent
engagement at the University of Wyoming as Project Controls Manager for the
construction of a coal gasification research and technology development
center, functioned as Owner’s Representative and trained members of the
facilities planning group in the use of P6. Prior assignments include Lead
Project Scheduling and Project Controls Manager of power plant construction /
outages for utilities, AE and construction firms, and service providers
including Xcel Energy, Blattner Energy, Burns & McDonnell, Skanska USA,
Northeast Utilities, PSE&G, GE Power Systems, NAES, and Bechtel. In
a key role with Burns & McDonnell as Senior Project Controls Lead for the
Northeast Utilities NEEWS T&D Project, developed schedule baselines and
CPM project schedules in P6 for a major 4 section T&D project consisting
of 6,000 scheduled activities and over 100 miles of underground and above
ground transmission. Also developed schedules for 31 planned PSNH
T&D projects with budgets ranging from $10M to $300M. Critical path
analysis expert. Extensive experience converting older MS Project and earlier
versions of Primavera P3 to P6. Holds
a BS from the University of Massachusetts and is proficient in a broad range
of scheduling, project, plant, and inventory management applications
including Oracle Primavera, SAP, INDUS Passport, and MAXIMO. Experience: TVA Watts Bar Dual Unit
Scheduling Transition Manager
Aug 2014 to present Project Controls Manager – P6-Maximo 7.5 Upgrade Brought in to lead the
transition to dual unit work control using P6. Also, site DBA for P6.
Currently working on Maximo 7.5 upgrade testing and verifying the bridge
between P6 and Maximo is designed correctly. Responsible for cleaning up the
filters that feed the performance indicators resulting in most acceptable
work week performance trend since plant opened. Burns and McDonnell
Jun 2013 to May 2014 Project Controls Manager – Phillips 66 projects Contracted to develop
detailed C3, C4, C5 EPC project schedule as well as full supporting cash flow
and manhour loading. Developed manhour loaded level 3 FEL-3 and detailed
design schedules in Oracle Primavera P6 v8.3. Result: BMcD awarded the
engineering for a $1.4b export grade propane facility. Exelon Nuclear
Dec 2012 to May 2013 Project Controls Manager – Fort Calhoun Recovery Brought in to make
engineering recovery scheduling group more efficient and effective. Developed
WBS that facilitated combining 72 engineering projects supported by 8
contract schedulers into a single 12,000 task schedule supported by 2
contract schedulers. Moved to OCC to rebuild and make 32,000 task outage
schedule useable. Corrected WBS, reduced outage file to 12,000 tasks, cleaned
up the 48 page schedule log and reduced contract support staff from 8 to 3. Babcock power Company
Apr 2012 to Nov 2012 Principle Project Controls Engineer Created and updated
OEM product schedules for AQCS equipment manufacturer. Coordinated project
controls effort on 75Mwe Biomass EPC project for Florida Power. Exelon Nuclear
Nov 2011 to Mar 2012 Project Controls Manager - EPU Brought in to correct
baseline EPU schedule errors and produce production metrics in Excel.
Corrected WBS structure and combined 64 individual projects being supported
by 6 contract schedulers into 1 project supported by 1 scheduler. Cleared up
a 48 page schedule error log to create a fully integrated cpm schedule. Westinghouse NucleaR
Sep 2011 to Nov 2011 Sr. Project Scheduler Developed a detailed,
integrated baseline production schedules in P6 for the UAE contracts for RVI,
CRDMS, & RCP components manufacturing. Central Maine Power Co. -
Iberdrola USA
Mar
2011 to July 2011 Project Controls Manager – Iberdrola USA Developed a detailed
EPC schedules in P6 for ALL T & D projects in the Norhteast including
RG&E, NYSEG, and CMP. Developed monthly project controls report.
Responsible for all 3 locations as SNC could not properly staff the job.
Subsequently their scope was drastically reduced. Blattner Energy
Oct 2010 to Jan 2012 Project Controls Manager – BP Wind Power Project Developed a detailed,
integrated EPC Baseline schedule in P6 for a 250Mw, 125 tower wind farm
project. Blattner was directed by client to secure a P6 person to develop a
baseline to replace the MS Project schedule that they rejected per contract
requirement. Baseline of 3000 activities was built and approved in 5 weeks
allowing $14.4m in change orders to be submitted, all of which were
subsequently approved as well as 7 months of stranded invoices. University of Wyoming
Apr 2010 to Sep 2010 Project Controls Manager - Coal Gasification Advanced Technology
Center Hired by the
University of Wyoming to install Primavera and train two members of their
capital projects group in the use of P6. Also assigned to be the owner’s
representative in a joint venture between GE Energy and UW to construct a
coal gasification research and technology development center in Cheyenne,
Wyoming. Xcel Energy
Jan 2009 to Sept 2009 Senior Project Scheduler - Refueling Outage at
Monticello Nuclear Generating Station Was responsible for
analyzing the outage critical path daily and recommending corrections to
negative float. Resource-leveled operations department resources to increase
outage efficiency. Designed and produced resource analysis graphics (earned
vs. estimated man hours). Verified WO status in Indus Passport. Blattner Energy
Apr 2008 to Dec 2008 Project Controls Manager - Wind Power projects Developed a detailed,
integrated EPC schedule in P3 for a 100Mw wind farm project. Loaned to
TetraTech to baseline three projects in Wyoming in P3 due to owner refusal to
pay invoices that were not submitted per contract requirements. Re-baselined
three 160-tower wind projects simultaneously by training the individual
project managers in P6 scheduling. Projects were very similar in scope with a
total project value of $1B. Burns & McDonnell
Apr 2007 to
Mar 2008 Sr. Project Controls Lead for AE firm - NEEWS
T&D Project, September 2007 to March 2008 Developed a baseline
schedule for the Northeast Utilities New England East-West Solution T&D
Project. Rebuilt and maintained CPM project schedule in P3e and input baseline
cost planning at WBS level 2. The NEEWS project included four sub-projects,
6,000 scheduled activities, and over 100 miles of underground and above
ground transmission. Project Controls Manager – 850Mw Supercritical
Coal-fired Power Plant, April 2007 to September 2007 Hired to rebuild the
project baseline for AE firm. Required completely rebuilding WBS and a
massive detail reduction to the project CPM schedule to resolve reported
percent complete and invoicing issues. The Spear Group
Oct 2006 to Mar 2007 Project Controls Support at PSNH - Transmission
& Distribution CPM scheduler Developed CPM project
schedules for PSNH’s 5-year planned capital projects in PERT format for
project manager and contractor reviews prior to bid award. This group of 31
T&D projects included 4,500 total scheduled activities with project
budgets ranging from $10M to $300M. Project schedules were created from
scratch and involved collaborating with engineering in developing bid proposals
and working in the field with contractors to obtain weekly quantities and
forecasts. ·
Scheduled an 11-mile new 345kv line installed by J.C. Reed
in the Raymond, NH area. Project was finished three months ahead of schedule
and was the first PSNH T&D project with no change orders. Northrop Grumman
Jan 2006 to Sept 2006 Project Controls Manager - IT Software Development
for DoD Conversion from MS
Project to P3 for over 30 DoD projects where payment had been withheld
because invoices were not being submitted per DO specifications.
Completed conversion and did IBR in 21 days. ConocoPhillips Alaska
Aug 2005 to Dec 2005 Project Controls Lead - North Slope 2006 Capital
Projects Planning Developed detailed CPM
schedules in P3e for 2006 North Slope construction projects. Schedules
included all logistics planning of materials and trailer movement due to ice
roads availability. The Spear Group
Aug 2004 to Aug 2005 Senior Project Controls Support at Vermont Yankee -
Power Uprate Project Lead Planner Maintained the weekly
engineering CPM schedule in P3 for the engineering work control group. ·
Developed baseline EPU project schedule as lead project
scheduler. Skanska USA
Dec 2002 to Jul 2004 Project Controls Manager - 500Mw 2x1 7FA CC Power
Plant Was responsible for
all construction subcontractor work sequencing, coordination, and scheduling.
Reviewed and approved all subcontractor invoices and material submittals.
Responsible for estimating and submitting all change orders and monthly
invoices. Developed WBS for construction cost/quantity tracking. Performed
schedule CPM analysis daily. · Developed
P3 project level 2 CPM schedule and detailed project level 3 work schedules
for quantitative earned value invoicing. Produced monthly report including
cost, earned percent complete, and schedule forecasts. ·
Designed layouts in P3 for monthly earned value, earned
monthly invoice amount, and all commodity curves. PSEG Generation Group
Jun 2002 to Nov 2002 Project Controls Manager - Lawrenceburg Energy
Center Project (Owner’s Rep) A short-term
assignment at the request of owner to establish a firm projection of when
this project was going to be completed based upon the GC performance rates
for piping and electrical. Produced management presentation in four weeks
using Primavera and Excel, resulting in a GC $19m credit to owner. PG&E National Energy
Group
Sept 2000 to May 2002
Project
Construction Manager - I-195 Relocation Project, December 2000 to May 2002
All phases of
project management including but not limited to project cost, scheduling, and
monthly reports. Oversaw all contractor activity to verify adherence to
PG&E engineering specifications for material and labor. Construction
subcontractor work sequencing, coordination, and scheduling; reviewed and
approved all change orders and monthly invoices. Developed and
maintained project cost program. Implemented Primavera for all cost and
schedule graphics.
Project
Manager - Hydro Projects (Owner’s Rep), September 2000 to December 2000
Oversaw contractor to
verify adherence to PG&E engineering specifications for material and
labor submittals. Was responsible for all construction subcontractor work
sequencing, coordination, and scheduling. Managed, reviewed, and approved all
contracts, change orders and monthly invoices. GE Power
Systems
Oct 1999 to Sept 2000 Project Controls Manager, CC
Power Plants - July 2000 to September 2000 Led project controls team in developing Primavera
project schedule template for 7FA simple cycle power plants. ·
Developed systemized startup schedule sequence to improve
CPM schedule analysis and startup of turnkey plants. Project Controls Manager, 2x1 GE
7FA CC Power Plant - Oct 1999 to Jul 2000 Was responsible for EPCC schedule and client/contractor
reporting interface. Integrated all subcontractor schedules and resource
loaded. Developed systematic startup schedule as well as startup system
boundaries and turnover packages.
Coca
Cola
Oct 1997 to Oct 1999
Project Controls Manager SAP/R3 software
implementation and configuration of the IM and PS modules at Coca-Cola. Was
responsible for the interface development between SAP/R3 and Primavera.
Trained all project personnel in CPM planning and scheduling. National
Semiconductor
Jul 1997 to Sept 1997 Startup
Scheduler for chip capacity
expansion at a large semiconductor facility. Created startup schedule
in Primavera. Northeast Utilities
Sept 1996 to Jul 1997 Project Controls Manager – Millstone Station Developed integrated, resource-loaded schedules and
linked them to a MS Access database for tracking and trending. ·
Recognized by the utility as the CPM/PERT critical path
analysis expert and mentored personnel. North Atlantic Energy
Services
Jul 1996 to Sept 1996 Project Controls Manager -
Seabrook Developed detailed
manpower schedule to assist plant management in creating 1997 budget request.
Assisted in the transition to Primavera planning and scheduling platform and
in the implementation of Indus Passport. International
Paper Co
Oct 1995 to Jun 1996 Project Engineer – Hydro Projects Trained project engineers and managers
in the use of planning and scheduling tools as well as integrated cost
control techniques, especially Primavera v3.1 for windows.
Commonwealth Edison Co
Jan 1987
to Sept
1995
Project Controls Manager, June 1987 to September
1995 Completed successful business process re-engineering
of the outage and maintenance planning and scheduling groups. · Established
resourced outage planning and scheduling programs. · Designed
and implemented a planning, scheduling, and maintenance work order tracking
system. ·
Was Outage Coordinator for all site planning and support
for capital projects under $25m. Lead Startup Scheduler, 35mw Cogeneration Plant -
January 1987 to June 1987 Developed startup,
test, and checkout schedule using Primavera. Defined all system boundaries
for plant startup. Oversaw mechanical equipment installation and subcontracts
administration. Bechtel Power
Corp.
Oct 1984 to
Dec 1986 Senior Project Controls Engineer Planning, estimating, and cost control of several
nuclear retrofit projects and refuel outages. ·
CPM/PERT critical path instructor for energy services
division. C.T. Main Construction
Co
Jan 1982 to Sept
1984 Project Controls Engineer Planned pulp and paper
maintenance shutdowns. As scheduler for Otis Hydro project, developed
construction CPM schedules, bid proposals, and estimates for firm fixed-price
and lump sum construction projects. Rust Engineering
Jun 1981 to Jan 1982 Project Controls Engineer - #1 Paper Mill Project
for S.D. Warren Paper Co., Was responsible for defining plant startup
boundaries and all existing plant process piping tie-ins. ·
Developed detailed resource-loaded shutdown, tie-in, and
startup CPM schedules. Project Controls Manager, Coal Conversion Power
Project - June 1981 to Sept 1981 Stone &
Webster
Oct 1980 to
Jun 1981 Construction Planner / Estimator Developed detailed
project estimates for hydro and pulp / paper proposals. Daniel Construction
Co
Apr 1978 to Oct 1980 Project Controls
Engineer for new paper mill,
TMP, and C0-gen boiler project($360m). EDUCATION BS Landscape
Architecture, University of Massachusetts SOFTWARE
EXPERIENCE Primavera (6.1, 7.0
& 8.3 - P6 certified 102/106) Prime Contractor MS Project and P3
to P6 conversions expert SAP PS, IM, PM
(certified) INDUS Passport MAXIMO 5.0 |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|